Toolkit - Gantt Chart and Kanban
Gantt Chart
This is the plan I made for 3D over my easter break. I had unfortunately spent too much time focusing on other projects and not enough time on this one. I should've made sure I had more time on this project especially because 3D is one of my weaker areas. Here is the Gantt Chart I made for Toolkit.
Gantt Chart Updated/ Revised (10/05/25)
I was able to keep up with gantt chart up until week 4. I greatly overestimated how long the sculpting process would take and ended spending the week just on that. Luckily, I had just finished one of my other projects so for the final week I was able to put most of my focus onto this project. In this updated Gantt Chart, I ended up having to move the Retopology and Texturing into the final week.
Here is a link to the Miro Board I've been using to manage my projects so you can see it better
https://miro.com/app/board/uXjVIfcpGzE=/?share_link_id=655866724727
Kanban
To help me further manage this project, I created a Kanban. I used this to help me manage a previous project and I find it quite helpful. It allows me to easily see what I've completed and what I need to work on.